1. | Original meter set assembly (MSA) & connection to houseline stub before work has begun. |
|
 |
2. |
Turn gas
off at manual valve upstream of meter. Note: If
manual valve is difficult to open, contact your
gas utility for assistance. |
|
 |
3. |
Loosen
meter swivel. |
|
 |
4. |
Take care
not to ruin gasket when removing union. Note: If
gasket is damaged, call your gas utility for replacement. |
|
 |
5. |
Remove
existing plumbing downstream of meter. |
|
 |
6. |
With original
plumbing removed, build new plumbing from structure
to meter. |
|
 |
7. |
Configure
new plumbing with CALIFORNIA Valve. |
|
 |
8. |
Use telfon
tape or liquid sealant on all joints. |
|
 |
9. |
Install
union gasket and new plumbing from meter to building. |
|
 |
10. |
CALIFORNIA
Valve must be installed level. Note: Use leveling
chain to confirm that the seismic valve is level. |
|
 |
11. |
Install
stablizer bracket (Unistrut or equivalent) to plumbing
(within 6" of seismic valve) and secure to
building. |
|
 |
12. |
Finish
meter plumbing system with CALIFORNIA Valve. Note:
For aesthetics, level the stabilizer bracket. |
|
 |
13. |
While
gas is still off, open seismic valve. Do
not open against gas pressure. |
|
 |
14. |
Turn gas
on at meter inlet valve; do not
use pipe wrench. Note: Open gas
valve slowly to prevent damage to regulator. |
|
 |
15. |
Use soapy
solution to check for leaks. |
|
 |
16. |
Apply
paint to all new plumbing to prevent rust. |
|